Construction Progress Update – Week of July 24

Construction Update – 7/24/17

from Ryan Nebel, Construction Superintendent

Activities occurring this week at GFCFS:

  • Roof sheathing is complete.
  • All interior framing will be complete by middle of next week.
  • Fascia board, soffit vent installation ongoing.
  • Roofing underlayment starts on Friday.
  • Roofing with asphalt shingles to follow.
  • Mechanical, electrical, and plumbing rough-in of walls started this week.
  • Brick veneer to start next week.