Construction Update – 7/3/17

from Ryan Nebel, Construction Superintendent

Activities occurring this week at GFCFS:

  • Wood framing of EXTERIOR shear walls ongoing. Will be complete by next Tuesday.
  • Wood framing of INTERIOR walls ongoing.
  • Light pole rough-in ongoing.
  • All rain leaders for downspouts have been installed.
  • All curb and gutter has been laid out.
  • Temp power to building has been installed and underground electrical to building is complete.