Activities occurring this week at GFCFS:

  • Concrete slab prep is ongoing.
  • Concrete slab pours slated for next week.
  • Brick mason finished interior shear wall foundations and pouring bond beam Thursday.
  • Termite treatment done last Saturday.
  • Underground Electrical rough-in ongoing inside of building.
  • Vacuum lines installed and tested.
  • Setting steel columns on Thursday.
  • Continue to haul out dirt from site.
  • Installing storm structures and storm line.
  • Sediment pond stabilized.
  • Activities occurring this week at GFCFS:
  • Concrete slab prep is ongoing.
  • Concrete slab pours slated for next week.