Construction Progress Update – Week of June 19

Construction Update – 6/19/17

from Ryan Nebel, Construction Superintendent

Activities occurring this week at GFCFS:

  • Concrete slab pour using a pump truck completed for half of building. (120 cubic yards poured. That’s 15 concrete trucks.)
  • Sprinkler line installed inside pump room.
  • Electrical rough-in.
  • Concrete slab prep of remaining half of building.
  • Scale frame arrived and set in stockroom slab.
  • Backfill of footings on outside perimeter of building.
  • Grading entrance and grading curb and gutter.
  • All storm lines and storm structures commpleted.
  • Ready to start wood framing. Tomorrow, begin laying out walls and rooms in the building.