Free Clinic:  804-556-5840
Family Services:  804-556-6260
Clothes Closet:  804-556-3627

News & Events

Home > News & Events > Construction Progress Update – Week of November 13

Construction Progress Update – Week of November 13

Construction Update – 11/23/17

from Ryan Nebel, Construction Superintendent

  • Vinyl flooring installed throughout dental area
  • Installing switches and receptacles throughout building
  • Spot priming and spots point up of walls
  • Walls almost ready for finish paint
  • Install basestone throughout parking lot
  • Completed force main connections from old building and new building and tied into e existing manhole across Route 6
  • Installed bathroom accessories and toilet partitions
  • Testing and balancing of HVAC system
  • Finished installation of slat walls in Clothes Closet
  • Setting plumbing fixtures and sinks throughout building
  • Mounted light sconces around exterior of building