Construction Progress Update – Week of October 9

Construction Update – 10/9/17

from Ryan Nebel, Construction Superintendent

  • Dominion Power installed permanent power to building
  • Completed 50% of light fixtures installation in ceilings
  • Completed 75% mechanical grills and diffusers in ceilings
  • Completed hardieplank siding
  • Completed all exterior soffit trim
  • Started install of lay-in ceiling tiles
  • All flooring delivered; all flooring supplies now onsite
  • All ceiling tiles delivered and now onsite
  • Poured HVAC equipment pads
  • Installed exhaust fans