Construction Update – 9/18/17

from Ryan Nebel, Construction Superintendent

  • Insulate attic with R-38 blown in insulation.
  • Set mechanical louvers.
  • Install electrical panelboards.
  • Fiber sement siding install around entire building.
  • Aluminum entrances and storefronts.
  • Prime/paint walls.