  • Install cast stone wainscot on top of brick veneer on all elevations.
  • Continue to hang sheetrock.
  • Continue Mechanical/Electrical/Plumbing rough-in in attic.
  • Rough-in light fixtures in hard ceilings.
  • Install temporary doors and temporary protection for polished concrete.