Construction Progress Update – Week of November 13

Construction Update – 11/23/17 from Ryan Nebel, Construction Superintendent Vinyl flooring installed throughout dental area Installing switches and receptacles throughout building Spot priming and spots point up of walls Walls almost ready for finish paint Install basestone throughout parking lot Completed force main connections from old building and new building and tied into e existing […]

Construction Progress Update – Week of October 16

Construction Update – 10/16/17 from Ryan Nebel, Construction Superintendent All flooring materials delivered Started ceramic tile installation Set all HVAC units Turned on permanent power to building Hung all doors and stared door hardware install Started wood shelving in storage rooms and stockrooms Installed data equipment Mobilized heavy equipment for sitework Finished light fixture installation […]

Congratulations, Diane Reale, Great Nonprofit Boss of 2017

Congratulations to our own Diane Reale, Director of Volunteer Resources, on her selection as a 2017 Great Nonprofit Boss. Diane is one of 25 honorees chosen for recognition by the Young Nonprofits Professionals Network RVA. A celebration for award winners, their friends, and colleagues will be held Wednesday, November 1, 6 – 8pm, at the […]

Construction Progress Update – Week of October 9

Construction Update – 10/9/17 from Ryan Nebel, Construction Superintendent Dominion Power installed permanent power to building Completed 50% of light fixtures installation in ceilings Completed 75% mechanical grills and diffusers in ceilings Completed hardieplank siding Completed all exterior soffit trim Started install of lay-in ceiling tiles All flooring delivered; all flooring supplies now onsite All […]

Construction Progress Update – Week of October 2

Construction Update – 10/2/17 from Ryan Nebel, Construction Superintendent finished prime painting walls throughout building finished framing acoustical ceilings through building finished hanging last areas of sheet rock set louvers connecting power panelboards and pulling wire to terminals relocated red shed to building site finished cutting in sprinkler heads in ceiling installed mechanical grilles and […]

Construction Progress Update – Week of September 25

Construction Update – 9/25/17 from Ryan Nebel, Construction Superintendent primed painting walls throughout building framed acoustical ceilings throughout building connected permanent power and removing temporary power service pulled construction trailer office from job site set lights and mechanical grills in ceiling hung sheet rock on all hard ceilings completed Hardie plank siding and all window […]

Free Mammograms – October is Breast Cancer Awareness Month

FREE MAMMOGRAPHY In commemoration of Breast Cancer Awareness Month, the Ellen Shaw de Paredes Institute for Women’s Imaging is continuing its support of the early detection of breast cancer by offering free screening mammography each Wednesday in October. WEDNESDAY, OCTOBER 4 WEDNESDAY, OCTOBER 11 WEDNESDAY, OCTOBER 18 and WEDNESDAY, OCTOBER 25 4:00 PM – 6:30 […]

Volunteer Spotlight – Ed Lehre

by Alexandra Herrera and Quinta Pace (GFCFS volunteers from Goochland High School) El Lehre, a volunteer at the Goochland Free Clinic is 72 years of age and was born and raised in California. He attended the United States Naval Academy in Annapolis. Ed moved to Goochland with his wife in 1981 and built their home […]

Construction Progress Update – Week of September 18

Construction Update – 9/18/17 from Ryan Nebel, Construction Superintendent Insulate attic with R-38 blown in insulation. Set mechanical louvers. Install electrical panelboards. Fiber sement siding install around entire building. Aluminum entrances and storefronts. Prime/paint walls.

Construction Progress Update – Week of September 11

Construction Update – 9/11/17 from Ryan Nebel, Construction Superintendent Install cast stone wainscot on top of brick veneer – all elevations. Finish hanging sheetrock and start prepping for paint. Install mechanical duct throughout entire building. Installesprinkler pipe throughout entire building. Continu electrical rough-in throughout building. Hang cement board in bathrooms for tile prep. Blade off […]